Case Studies

Audio Visual Case Study

Working for one of our partners, the project consisted of Installing of 250 interactive screens across 12 sites in various locations including Nottinghamshire, Staffordshire, Northampton, Milton Keynes & Norfolk.

Scope of works

  • Site Survey 250 classrooms
  • Project Management
  • De-Installation of existing equipment
  • Installation
  • Testing & Commissioning
  • General waste disposal of non-electrical existing equipment
  • WEEE Disposal of existing equipment
  • Re-decoration of walls

Our team were initially engaged six weeks prior to the completion deadline. Our pre-sales team conducted site surveys of all 250 classrooms within a week and processed all the information including specific recommendations for rooms that required alternative solutions.

Our project manager ensured that everything was co-ordinated to ensure a smooth delivery of the project.

Engineering teams were allocated and deployed to each of the 12 sites, de-installed all the existing equipment and all installations were completed, tested and signed off within four weeks which was ahead of the deadline.

The project proved such a success that our partner received an additional order for 50 units which have since been deployed.

Network Infrastructure Case Study

Working to a tight deadline our partner needed a quick response to install network cabling, network points, wireless access points in time for the opening of a new building.

Scope of works

  • CAT 6 cabling
  • Installation of wireless access points
  • Installation of network points
  • Rack build
  • Cable Testing

We conducted a site survey within 2 days of the initial engagement. Equipment and engineers were deployed the following week and the installation signed off within 7 days, two days prior to the opening date.

The building structure presented a challenge for our team. Cabling routes were difficult which determined that all cabling would need to be housed in surface mount trunking. Our team ran 200m of CAT 6 cabling housed in surface mount trunking across four floors, 15 wireless access points and in excess of 20 network points. All cabling terminated into a patch panel in a wall mounted equipment rack. The team tested each individual cable run before handing over to our partner.

Our partner’s customer was delighted with the end result and that all had been achieved in such a short timescale.

Electrical Installation case study

Our partner required double power sockets for each screen within a large-scale digital signage deployment.

Scope of works

  • Installation of double power sockets
  • Testing and certification

Our electricians utilised the existing electrical infrastructure to install a significant number of additional power sockets within a large office complex. All worked was completed, tested and certified within a day which exceeded expectations.

Our Audio-Visual engineers attended the following day and installed all the digital signage screens which concluded the full project implementation within 2 days.